Size: 6085
Comment:
|
Size: 2534
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 1: | Line 1: |
== SCinet20 Contributor Portal == | == SCinet24 Contributor Portal == |
Line 3: | Line 3: |
'''Relevant Documents/Reference Information''' | '''Contributor Information''' |
Line 5: | Line 5: |
[[attachment:SC20 SCinet Contributor Relations Guide.docx | SC20 Contributor Guide.docx]] | [[https://docs.google.com/forms/d/e/1FAIpQLSc8omo1NFMLSYK1VwC0lfyN5XNE7WjPgKAJwDOJuvHOkFbBhA/viewform| Intent to Participate & Contact Form in SCinet 2024]] |
Line 7: | Line 7: |
{{{#!wiki comment [[https://docs.google.com/document/d/1icX2nB_xuXGpi_mcidL99SJW7UkT-CXi/edit# | SC24 SCinet Contributor Guide.docx]] }}} |
|
Line 8: | Line 11: |
=== SCinet Approved Logo Information === [[attachment:SC20 SCinet Logo Guide.pdf]] |
[[attachment:sc24_logosheet.ai| SC24 Logos and Color Guide (PDF)]]] [[attachment:SCinet Contributor Webinar 2023.m4v|(old) SCinet 2023 Contributor Relations Webinar Recording (m4v)]] [[attachment:SCinet Contributor Webinar 2023 slides.pdf|(old) SCinet 2023 Contributor Relations Webinar Slides]] {{{#!wiki comment [[https://drive.google.com/drive/folders/163lmw4Q0GyWR3CGkWIl3RlcTySZEUqYi| SCinet 2023 Contributor Relations Webinar (recording)]] }}} '''Bill of Materials and Shipping Forms''' ''Will Be Released April 2024'' {{{#!wiki comment [[attachment:SCinet 2023 BOM.xlsx| SC24 Bill of Materials (BOM)]] [[attachment:SC23 Waiver of Liability.docx| SC24 Liability Waiver - Due with first BOM ]] [[attachment:SC23 SCINET - Warehouse Pre-Stage - Green.pdf| SC24 Shipping Label - Staging (Green) October 11th arrival in Freeman Warehouse ]] [[attachment:SC23 SCINET - Show Site Show Install - Purple.pdf| SC24 Shipping Label - Pre-show (Purple) November 6th arrival at the Convention Center]] }}} |
Line 12: | Line 36: |
'''''=== Please plan to provide the following deliverables. Please check back often as the dates may change. ===''''' | '''''Please plan to provide the following deliverables. Please check back often as the dates may change.''''' ||<tablewidth=""" tablestyle=""">'''Deliverable ''' ||'''Deadlines ''' ||'''Details ''' || ||Contributor Intent to Participate || Friday, May 24 2024 ||Contributors (or Team Leads) let CR know they intend to participate|| ||Initial BOM || Friday, June 28 2024 || First pass BOM to determine initial contributor tiers and equipment || ||Liability Waiver|| Friday, June 28 2024 || Required for contributors loaning hardware || ||Updated BOM|| Friday, August 9 2024 || Any updates since initial BOM || ||Final BOM||Friday, September 6 2024|| Final loans, equipment, software valuations || ||Outbound shipper paperwork|| Friday, September 6 2024|| Mandatory for return of hardware || ||Loaned Equipment Received Freeman|| Friday, October 18 2024|| Mandatory for hardware loans || |
Line 14: | Line 46: |
''''' ''''' ||<tablewidth=""" tablestyle=""">'''Deliverable ''' ||'''Deadlines ''' ||'''Details ''' ||Submission Information || ||Contributor Intent to Participate and Initial BOM || June 19 ||Read only file: [[https://drive.google.com/open?id=11CP6r5xDILAlmS4ftXeLaegtVbofaztk|Bill Of Materials template (.xls)]] (download or copy to your google drive)||[[mailto:logistics@scinet.supercomputing.org?cc=contributor-relations@scinet.supercomputing.org&subject=SC20 Bill of Materials Initial Submission|Submit Bill Of Materials (BOM) ]] Note: The BOM is used by SCinet to establish sponsorship levels, inventory, architecture and insurance coverage. All contributors need to submit a BOM (hardware, software, services) to receive contributor benefits''' || ||Final Equipment List for Insurance (Final BOM) ||July 24 ||Read only file: [[https://drive.google.com/open?id=11CP6r5xDILAlmS4ftXeLaegtVbofaztk|Bill Of Materials template (.xls)]] (download or copy to your google drive)||[[mailto:logistics@scinet.supercomputing.org?cc=contributor-relations@scinet.supercomputing.org&subject=SC20 Final Bill of Materials Submission|Submit Bill Of Materials (BOM) ]] || ||Liability Waiver ||July 24 ||[[https://drive.google.com/open?id=1jKz-yz5jH9cNh31vPfCc7ZcO5nayfhK2HrAyn9nwvq4 | Liability Waiver]]||[[mailto:logistics@scinet.supercomputing.org?cc=contributor-relations@scinet.supercomputing.org&subject=SC20 Liability Waiver|Submit Waiver/Liability Release ]] '''Note: Liability Waiver/Release only required if submitting equipment to show in Atlanta''' || ||Volunteer Travel Support Fund Donation Declaration ||August 7 ||$2,500 donation increases benefits valuation to the next sponsorship level ||[[mailto:logistics@scinet.supercomputing.org?cc=contributor-relations@scinet.supercomputing.org&subject=SC20 Volunteer Travel Support Fund Declaration|Declare Volunteer Travel Support Fund Support]] || ||Intention to provide SCinet20 Apparel ||August 7 ||Apparel donation increases benefits valuation to the next sponsorship level ||[[mailto:logistics@scinet.supercomputing.org?cc=contributor-relations@scinet.supercomputing.org&subject=SC20 Intention to Provide SCinet Apparel|Intention to Provide SCinet Apparel]] || ||Company Logo submission ||August 21 ||Submit logo to Contributor Relations || [[mailto:contributor-relations@scinet.supercomputing.org&subject=SC20 Company Logo|Submit Company Logo]]|| ||SCinet Contributor Highlights for Interactive Experience Kiosk submission ||August 28 ||Submit information to Contributor Relations || [[mailto:contributor-relations@scinet.supercomputing.org&subject=Partner Highlights for Kiosk|Submit Contributor Highlights for Kiosk]]|| ||Wall Panel Artwork submission ||September 25 ||Submit information to Contributor Relations. Based on Contributor Sponsorship Level (Gold and Above) - [[attachment:freeman-graphics-artwork-guidelines.pdf|Specifications for Panel Artwork]] || [[mailto:contributor-relations@scinet.supercomputing.org&subject=Wall Panel Custom Artwork|Submit Wall Panel Custom Artwork]]|| ||Request Network Connection Transfer/Modification ||October 16 || Please send your request to Contributor Relations. 10Gbps and 100Gbps upgrades include connection only. Router and Optics not provided.||[[mailto:logistics@scinet.supercomputing.org?cc=contributor-relations@scinet.supercomputing.org&subject=SC20 Request Network Connection Transfer|Request Network Connection Transfer]] || ||Request Complimentary Exhibitor Badges ||October 16 ||Provide recipient(s) Full Name and Email Address ||[[mailto:logistics@scinet.supercomputing.org?cc=contributor-relations@scinet.supercomputing.org&subject=SC20 Request Complimentary Exhibitor Badges|Request Complimentary Exhibitor Badges]]. *Number of complimentary badges are based on sponsorship level. || ||Tracking Information Submitted ||October || All shipping tracking information must be sent via email to Logistics. Without this information, we cannot ensure your equipment will be safely delivered to SCinet||[[mailto:logistics@scinet.supercomputing.org?cc=contributor-relations@scinet.supercomputing.org&subject=SC20 Shipping Tracking Info|Submit Shipping Tracking Information]] || ||Items Arrive at Freeman Warehouse ||October 9 || [[attachment:SC20 SCINET - Warehouse Pre-Stage - Green.pdf|Shipping Label]] Shipping Phone: 1-303-329-3442|| '''Items arriving after this date cannot be guaranteed to make it to SC20 on time'''|| ||Final BOM Submitted/Benefit Value Finalized ||October 16 ||Work with SCinet Technical Team Leads || || ||Donated SCinet19 Apparel Received ||October 16||Use Approved SCinet Shipping Label above || [[attachment:SCinet20_Apparel_Sizes_and_Quantities.pdf|Apparel Sizes and Quantities]][[attachment:SCinet emb revised 10 10[1].DST|Embroidery DST File]] [[attachment:SCinet Final two locations polo[1].pdf|Example Embroidered Shirt]]|| ||Outbound Shipping Paperwork Submitted ||November 21 || [[attachment:Outbound-Shipping|Outbound Shipping Request]] [[attachment:Handy-Carry| Outbound Shipping Request (Hand Carry)]]||Discuss with SCinet Team Lead || || || || || || === 2020 Contributor Logos === Please send an email to [[mailto:contributor-relations@scinet.supercomputing.org&subject=SC20 Contributor Logo|SCinet20 Contributor Relations]] with a logo for 2020. ||'''__Entity Name__''' ||'''__Approved__''' ||'''__As of Date__''' ||'''__Logo File__''' ||'''__Reason__''' || |
|
Line 43: | Line 50: |
[[mailto:contributor-relations@scinet.supercomputing.org&subject=SCinet20 Inquiry|Contact SCinet20 Contributor Relations]] | [[mailto:contributor-relations@scinet.supercomputing.org&subject=SCinet24 Contributor Inquiry|Contact SCinet24 Contributor Relations]] |
SCinet24 Contributor Portal
Contributor Information
Intent to Participate & Contact Form in SCinet 2024
SC24 Logos and Color Guide (PDF)]
(old) SCinet 2023 Contributor Relations Webinar Recording (m4v)
(old) SCinet 2023 Contributor Relations Webinar Slides
Bill of Materials and Shipping Forms
Will Be Released April 2024
Deliverables, Deadlines and Details
Please plan to provide the following deliverables. Please check back often as the dates may change.
Deliverable |
Deadlines |
Details |
Contributor Intent to Participate |
Friday, May 24 2024 |
Contributors (or Team Leads) let CR know they intend to participate |
Initial BOM |
Friday, June 28 2024 |
First pass BOM to determine initial contributor tiers and equipment |
Liability Waiver |
Friday, June 28 2024 |
Required for contributors loaning hardware |
Updated BOM |
Friday, August 9 2024 |
Any updates since initial BOM |
Final BOM |
Friday, September 6 2024 |
Final loans, equipment, software valuations |
Outbound shipper paperwork |
Friday, September 6 2024 |
Mandatory for return of hardware |
Loaned Equipment Received Freeman |
Friday, October 18 2024 |
Mandatory for hardware loans |
Questions, comments or concerns?