== SCinet22 Contributor Portal == | == SCinet23 Contributor Portal == |
Line 3: | Line 3: |
'''Relevant Documents/Reference Information''' | '''Contributor Information''' |
Line 5: | Line 5: |
[[https://forms.gle/XHXCMhWCerKi6Lov7|Vendor Contact Form/Intent to Participate in SCinet 2022]] | [[https://forms.gle/pfuCd48iTLk9XwwbA| Intent to Participate & Contact Form in SCinet 2023]] |
Line 7: | Line 7: |
[[https://docs.google.com/document/d/1icX2nB_xuXGpi_mcidL99SJW7UkT-CXi/edit# | SC22 Contributor Guide.docx]] | [[https://docs.google.com/document/d/1icX2nB_xuXGpi_mcidL99SJW7UkT-CXi/edit# | SC23 SCinet Contributor Guide.docx]] |
Line 9: | Line 9: |
[[attachment:SCinet 2022 CR Webinar.mp4 | SC22 CR Webinar Presentation ]] and [[https://docs.google.com/presentation/d/14nEJsi7EeRZBh2TG3_ySKJjxFD10hPZuDd6yXVJABHQ/edit?usp=sharing | slides ]] | [[attachment:SC23 logo color sheet.pdf| SC23 Logos and Color Guide (PDF)]] |
Line 11: | Line 11: |
[[attachment:SC22 Logos and Colors.pdf | SC22 Logos and Color Guide (PDF)]] | [[attachment:SCinet Contributor Webinar 2023.m4v|SCinet 2023 Contributor Relations Webinar Recording (m4v)]] |
Line 13: | Line 13: |
[[https://docs.google.com/spreadsheets/d/1HSI5tcKd76nuNmz1BeIrNaOllWfH4K9G/edit?usp=sharing&ouid=110379968562830532135&rtpof=true&sd=true | SC22 Bill of Materials (BOM) (can also be used for Architectural Equipment Identification)]] | [[attachment:SCinet Contributor Webinar 2023 slides.pdf|SCinet 2023 Contributor Relations Webinar Slides]] |
Line 15: | Line 15: |
[[https://docs.google.com/document/d/1tZQFCRKFaJudRFaJib8ikr2ttZKXlozUZJUpjuWhrmU/edit?usp=sharing | SC22 Liability Waiver - Due with first BOM ]] | {{{#!wiki comment [[https://drive.google.com/drive/folders/163lmw4Q0GyWR3CGkWIl3RlcTySZEUqYi| SCinet 2023 Contributor Relations Webinar (recording)]] }}} |
Line 17: | Line 19: |
[[attachment:SC22shipping-prestage.pdf | SC22 Shipping Label - Staging (October 15th arrival in Freeman Warehouse) ]] | '''Bill of Materials and Shipping Forms''' |
Line 19: | Line 21: |
[[attachment:SC22shipping-show.pdf | SC22 Shipping Label - Preshow (November 7th arrival at the Convention Center) ]] | [[attachment:SCinet 2023 BOM.xlsx| SC23 Bill of Materials (BOM)]] [[attachment:SC23 Waiver of Liability.docx| SC23 Liability Waiver - Due with first BOM ]] [[attachment:SC23 SCINET - Warehouse Pre-Stage - Green.pdf| SC23 Shipping Label - Staging (Green) October 11th arrival in Freeman Warehouse ]] [[attachment:SC23 SCINET - Show Site Show Install - Purple.pdf| SC23 Shipping Label - Pre-show (Purple) November 6th arrival at the Convention Center]] |
Line 22: | Line 30: |
{{{#!wiki comment [[attachment:SCinetContributorsBrochure-2021.pdf | SC21 Contributor Brochure]] [[attachment:SCShippingLabel.pdf | SC21 Shipping Labe (Green) - Used for all freight shipments]] [[attachment:NonFreightShippingLabel.pdf | SC21 Non-freight shipping label (Purple) - Used for apparel and smaller UPS/Fedex Non-freight items for setup]] }}} {{{#!wiki comment [[attachment:SCinet Contributors Brochure - 2020.pdf | SC20 Contributors Brochure]]. <--- Needs updated [[attachment:SCinet21 Blank BOM.xlsx | SC21 Blank Bill of Materials]] }}} '''2022 Contributor Relations Webinar Links''' Tuesday, May 10, 4pm Eastern: [[https://tinyurl.com/TuesCRWebinar || tinyurl.com/TuesCRWebinar Link ]] Thursday, May 12, 2pm Eastern: [[https://tinyurl.com/ThursCRWebinar | tinyurl.com/ThursCRWebinar Link ]] Video and slide links will be here after the first Webinar is done. {{{#!wiki comment === SCinet Approved Logo Information === [[attachment:SC21 Logo Color Guide.pdf | SC21 Logo Color/Thread Guide (PDF)]] }}} |
|
Line 53: | Line 31: |
'''''=== Please plan to provide the following deliverables. Please check back often as the dates may change. ===''''' ||<tablewidth=""" tablestyle=""">'''Deliverable ''' ||'''Deadlines ''' ||'''Details ''' ||Submission Information || ||Contributor Intent to Participate || May 13 ||Contributors (or Team Leads) let CR know they intend to participate|| [[https://docs.google.com/forms/d/e/1FAIpQLSecxA4uwKjspna-L_3z8nmEiPx_fSvuuvPESZk17zVgtxmfMQ/viewform | Google Form]] or [[mailto:logistics@scinet.supercomputing.org?cc=contributor-relations@scinet.supercomputing.org&subject=SC22 Contributor Intent to Participate |Email intent to participate ]] || ||Architectural Equipment Identification (optional but encouraged) || May 20 || Very preliminary BOM-like document to help supply chains || [[https://docs.google.com/spreadsheets/d/1HSI5tcKd76nuNmz1BeIrNaOllWfH4K9G/edit?usp=sharing&ouid=110379968562830532135&rtpof=true&sd=true | Use the blank BOM form]] || ||Initial BOM || July 15 || First pass BOM to determine initial contributor tiers and equipment || [[https://docs.google.com/spreadsheets/d/1HSI5tcKd76nuNmz1BeIrNaOllWfH4K9G/edit?usp=sharing&ouid=110379968562830532135&rtpof=true&sd=true | Blank BOM form]] || ||Liability Waiver|| July 15 || Required for contributors loaning hardware || [[https://docs.google.com/document/d/1tZQFCRKFaJudRFaJib8ikr2ttZKXlozUZJUpjuWhrmU/edit?usp=sharing | Liability Waiver]] || ''''' ''''' |
'''''Please plan to provide the following deliverables. Please check back often as the dates may change.''''' ||<tablewidth=""" tablestyle=""">'''Deliverable ''' ||'''Deadlines ''' ||'''Details ''' || ||Contributor Intent to Participate || May 12 ||Contributors (or Team Leads) let CR know they intend to participate|| ||Initial BOM || July 14 || First pass BOM to determine initial contributor tiers and equipment || ||Liability Waiver|| July 14 || Required for contributors loaning hardware || ||Updated BOM|| August 11 || Any updates since initial BOM || ||Final BOM||September 8|| Final loans, equipment, software valuations || ||Loaned Equipment Received Freeman|| October 11 || Mandatory for hardware loans || ||Outbound shipper paperwork|| October 27 || Mandatory for return of hardware || |
Line 81: | Line 60: |
|| || || || || |
|
Line 82: | Line 63: |
|| || || || || === 2022 Contributor Logos === |
|
Line 90: | Line 67: |
[[mailto:contributor-relations@scinet.supercomputing.org&subject=SCinet22 Inquiry|Contact SCinet22 Contributor Relations]] | [[mailto:contributor-relations@scinet.supercomputing.org&subject=SCinet23 Contributor Inquiry|Contact SCinet23 Contributor Relations]] |
SCinet23 Contributor Portal
Contributor Information
Intent to Participate & Contact Form in SCinet 2023
SC23 SCinet Contributor Guide.docx
SC23 Logos and Color Guide (PDF)
SCinet 2023 Contributor Relations Webinar Recording (m4v)
SCinet 2023 Contributor Relations Webinar Slides
Bill of Materials and Shipping Forms
SC23 Liability Waiver - Due with first BOM
SC23 Shipping Label - Staging (Green) October 11th arrival in Freeman Warehouse
SC23 Shipping Label - Pre-show (Purple) November 6th arrival at the Convention Center
Deliverables, Deadlines and Details
Please plan to provide the following deliverables. Please check back often as the dates may change.
Deliverable |
Deadlines |
Details |
Contributor Intent to Participate |
May 12 |
Contributors (or Team Leads) let CR know they intend to participate |
Initial BOM |
July 14 |
First pass BOM to determine initial contributor tiers and equipment |
Liability Waiver |
July 14 |
Required for contributors loaning hardware |
Updated BOM |
August 11 |
Any updates since initial BOM |
Final BOM |
September 8 |
Final loans, equipment, software valuations |
Loaned Equipment Received Freeman |
October 11 |
Mandatory for hardware loans |
Outbound shipper paperwork |
October 27 |
Mandatory for return of hardware |
Questions, comments or concerns?